ISLAND ROADS UPDATE – FRESHWATER BAY AREA

Posted on: 12th March 2025

Written By: Melanie Gardiner

Category Latest News

Island Roads schedule of works for Freshwater Bay area.

Island Road Schedule of Works for the Freshwater Bay area. Timing of the works: • Localised pre-works are due to start 11th March 2025 for approximately 4 working days. • Works will take place during the day between 08:00 – 16:00. • The works will be followed by a second surface dressing treatment to the whole road during April/May (which will take approximately 2 hours) followed by a sealant approximately 4 days later (4 hours). Further information including dates will be communicated at a later date. • Advance warning boards with start and end date will be erected before works commence. Works Information • 08:00 – 16:00 (on each day / weekdays only) • Guyers Road, Freshwater – from Victoria Road to Gate Lane (area of works marked in red on the attached plan). Time of works Safety measures during works: • A 24-hour road closure will be required at all times throughout the works for safety reasons. • Vehicle access will be prohibited at all times within the area of works. • Only when it is safe to do so, resident access will be maintained within the road closure extent outside of the area of works. • Should you require your vehicle during the dates of work we would recommend parking in an alternative location. • “No Parking” cones will be placed out the night prior to works commencing. • Pedestrian access will be maintained. • Emergency vehicle access will be maintained.
Island Roads schedule of works for the Freshwater Bay area. Timing of the works: • Localised pre-works are due to start 13th March 2025 for approximately 3 working days. • Works will take place during the day between 08:00 – 16:00. • The works will be followed by a second surface dressing treatment to the whole road during April/May (which will take approximately 2 hours) followed by a sealant approximately 4 days later (4 hours). Further information including dates will be communicated at a later date. • Advance warning boards with start and end date will be erected before works commence. Works Information • 08:00 – 16:00 (on each day / weekdays only) • Guyers Road, Freshwater – from Victoria Road to Gate Lane (area of works marked in red on the attached plan). Time of works Safety measures during works: • A 24-hour road closure will be required at all times throughout the works for safety reasons. • Vehicle access will be prohibited at all times within the area of works. • Only when it is safe to do so, resident access will be maintained within the road closure extent outside of the area of works. • Should you require your vehicle during the dates of work we would recommend parking in an alternative location. • “No Parking” cones will be placed out the night prior to works commencing. • Pedestrian access will be maintained. • Emergency vehicle access will be maintained.
Island Roads schedule of works for the Freshwater Bay area. Timing of the works: • Localised pre-works are due to start W/C 17th March 2025 for approximately 2 working days. • Works will take place during the day between 08:00 – 16:00. • The works will be followed by a second surface dressing treatment to the whole road during April/May (which will take approximately 2 hours) followed by a sealant approximately 4 days later (4 hours). Further information including dates will be communicated at a later date. • Advance warning boards with start and end date will be erected before works commence. Works Information • 08:00 – 16:00 (on each day / weekdays only) • Victoria Road, Freshwater – from Guyers Road to Bedbury Lane Freshwater (area of works marked in red on the attached plan). Time of works Safety measures during works: • A 24-hour road closure will be required at all times throughout the works for safety reasons. • Vehicle access will be prohibited at all times within the area of works. • Only when it is safe to do so, resident access will be maintained within the road closure extent outside of the area of works. • Should you require your vehicle during the dates of work we would recommend parking in an alternative location. • “No Parking” cones will be placed out the night prior to works commencing. • Pedestrian access will be maintained. • Emergency vehicle access will be maintained.

Related Posts

Afton Marsh Footpath Closure

Please be advised that the permissive path across Afton Marsh, running from Blackbridge Road and connecting to Public Footpath F36, has been temporarily closed while Gift to Nature undertakes improvement works at this countryside site. For information on the work being carried out please contact Gift to Nature info@gifttonature.org.uk

It is anticipated that the closure will remain in place for approximately four weeks, although this may be subject to change depending on progress of the works.

Gabion works – Spinfish

The gabion works at Spinfish are now complete. The area has been grass seeded (but we need some rain) and the path is now open for use.